West Ave- Mountain Ave Sanitary Sewer & Water Main Installation

Project Update: November 10, 2017

All utility installation is complete and roadway paving operations will continue next week on St. Paul, Wisconsin, West, and Glenwood Avenue. Traffic control will remain in place until the permanent pavement and pavement marking has been installed on the roadways. The water main Fox River crossing is still scheduled to take place starting on November 27th. Please contact me if you have any questions regarding this project and have a good weekend.

PDF of Progess and current status of the project


West 4
The West Ave to Mountain Avenue Sanitary Sewer and Water Main project is planned to begin during the week of August 28th.  The project will include the replacement of water main and sanitary  sewer as shown on the attached exhibit. For the residents on Glenwood  Drive, street parking will be restricted due to the narrow width of the  road, and access to private driveways will be very limited during the  project. We apologize in advance for the inconvenience, and the  following temporary parking options will be allowed during construction:

On the east side of N. West Avenue (400 thru 600 block) and either side of Park Avenue (400 block): The current parking restrictions will be lifted to allow for long term  parking, including overnight. However please note, vehicles still must  be moved every 72 hours (3 days).

On the west side of N. West Avenue, parking restrictions will remain the same.

There  may also be temporary disruption of your water service during  connections to the new water main, however you will be given prior  notification. The entire project is expected to be completed by  mid-November and we ask for your patience during this time.

Please contact the Water Utility with any questions at 262-521-5272


Contact Person:

Chris Walter, P.E.
Utility Engineer, Waukesha Water Utility
262-409-4432
cwalter@waukesha-water.com

River Crossing
West 3