Arcadian Avenue Reconstruction Project - 2017

Project Update: August 18, 2017

 

 

This week the City’s contractor finished all watermain and lateral work on Arcadian. They also completed storm sewer work at Greenfield Avenue and Perkins Avenue.

Next week, the City’s contractor plans on finishing all remaining underground utility work and begin pavement, and sidewalk removals throughout the project.

During this time access will be maintained to all local business and local traffic.


 

Any further questions or concerns you may have please contact me.

 

Craig Ausen, P.E.

Project Engineer

City of Waukesha – Engineering Division

130 Delafield St. Waukesha, WI 53188

O: 262-524-3589

C: 262-349-6516

20170727_112132
Below is some information regarding switching the road reconstruction from Prairie Ave to Arcadian Ave.

Due to potentially re-aligning N. Prairie Avenue between the railroad tracks and St. Paul Ave, the planned 2017 reconstruction project is being delayed. It is planned to substitute the reconstruction with Arcadian Avenue.

The Arcadian Avenue project limits are from 250’ west of Eugene Ct. to east of N. Greenfield Ave.

The Arcadian Avenue project will involve a complete road reconstruction including replacement of pavement, curbs, approaches and handicap ramps. The utility upgrades include relaying portions of the water main and sanitary sewer and rehabilitating the storm sewer.   

The project is anticipated to start in early May and be complete by the end of October.  During construction, the road will be closed to through traffic. Access will be maintained to driveways for residents & businesses within the construction limits until the concrete pavement is placed. When the concrete pavement is placed, residents will lose access to driveways until the curb and approaches have been placed and cured.       

A letter to the residents along Arcadian has been sent out to let them know the project is occurring. The DPW’s construction map will also be updated on the website with this change.