Arcadian Avenue Reconstruction Project - 2017

 

 

Project Update: April 28, 2017

WE Energies is continuing their work on the small gas main on the north side of Arcadian Avenue.
Due to unseen circumstances, the May 1st closure will not happen until a later date. Arcadian Avenue will remain open to thru traffic with the same traffic control devices and lane shifts.
As soon the new full closure date is received, it will be posted.
Any questions or concerns may be directed to:


Craig Ausen, P.E.

Project Engineer

City of Waukesha – Engineering Division

130 Delafield St. Waukesha, WI 53188

O: (262) 524-3589

C: (262) 349-6516

Project map
Below is some information regarding switching the road reconstruction from Prairie Ave to Arcadian Ave.

Due to potentially re-aligning N. Prairie Avenue between the railroad tracks and St. Paul Ave, the planned 2017 reconstruction project is being delayed. It is planned to substitute the reconstruction with Arcadian Avenue.

The Arcadian Avenue project limits are from 250’ west of Eugene Ct. to east of N. Greenfield Ave.

The Arcadian Avenue project will involve a complete road reconstruction including replacement of pavement, curbs, approaches and handicap ramps. The utility upgrades include relaying portions of the water main and sanitary sewer and rehabilitating the storm sewer.   

The project is anticipated to start in early May and be complete by the end of October.  During construction, the road will be closed to through traffic. Access will be maintained to driveways for residents & businesses within the construction limits until the concrete pavement is placed. When the concrete pavement is placed, residents will lose access to driveways until the curb and approaches have been placed and cured.       

A letter to the residents along Arcadian has been sent out to let them know the project is occurring. The DPW’s construction map will also be updated on the website with this change.