Jefferson Ave, Oscar St. and Neighborhood Project

Project Update June 6, 2017



Utility construction work is scheduled to begin on Jefferson Ave, Oscar St, Greenway Terrace, Butler Dr, and in the intersection of Butler Dr and Rustic Way.  The work will include sanitary sewer and water lateral upgrades.  Disturbed pavement areas will be restored with new pavement curb to curb.  This project is not a total reconstruction of the roadway so in general we will not be replacing curb, driveways, or sidewalks.  The Common Council has awarded the contract to PTS Contractors, Inc., Green Bay, Wisconsin. 

 

The Contractor is planning to begin moving in construction equipment and material the week of June 12 with construction commencing Monday, June 19th (weather dependent) on the western limits of the project and proceeding east.  The completion date for the project is Friday September 1, 2017.


Pre-Construction Package sent out to Residents

Jefferson Ave, Oscar St, Greenway Terr, & Butler Dr/Rustic Way Intersection

The City will construct utility improvements on Jefferson Ave, Oscar St, Greenway Terrace, Butler Dr, and in the intersection of Butler Dr and Rustic Way beginning later this spring.  

The project involves upsizing the existing sanitary sewer from near the intersection of Jefferson & Oscar to the intersection of Greenway Terrace & Manhattan.  In addition, the sanitary sewer will be lined from the intersection of Greenway Terrace & Manhattan to the intersection of Butler & Jennifer.  Rerouting of a sanitary force main in the intersection of Butler Dr and Rustic Way will also be necessary.  The Water Utility will also replace a section of water main on Oscar St.  Disturbed pavement areas will be restored with new pavement curb to curb.  

This project is not a total reconstruction of the roadway so in general curb, driveways, or sidewalks will not be replaced.  The project is scheduled to be bid out in March, with tentative approval by the Common Council of the successful bid in April.

Pre-Notice Package sent to Neighbors

Project Contact Information:

Jonathan Schapekahm, P.E.
262-524-3584
jschapek@waukesha-wi.gov

Location map - Oscar Greenway etc