2017 Street Resurfacing

Project Update August 4, 2017



The 2017 project includes:
Madison Street : 200 feet+/- west of S. Grandview to Comanche Lane
Patricia Lane : Northview Road to Pebble Valley Rd
S. Comanche Lane (Madison St. to Minot Ln)
Crestwood Drive (S. Intersection S. Comanche to N. Intersection.)

Stark Pavement Corp. Inc. of Brookfield, is the General Contractor for this year’s project. S. Comanche Lane, and Crestwood Drive have been milled and the asphalt binder replacements have occurred, and half of the crack filling has been completed. The asphalt surface course pavement is tentatively scheduled to be paved next week, subject to the weather. The milling and pavement removals on Madison Street are also scheduled to begin next week.

The south half of Patricia Lane will be resurfaced and the north half will be reconstructed. The north half of Patricia Lane has been excavated and removed, and some stone has been placed. The curb and gutter installation on the north half is also tentatively planned for next week. Letters have been sent to residents on the north half of Patricia to inform them of the concrete curing times and driveway access restrictions. The south half is tentatively planned to be milled as their mill becomes available.

 
Project Contact:
Dave Buechl, P.E.
262-524-3582
Dbuechl@waukesha-wi.gov