Saratoga Complex LED Lighting Upgrade

Project Update August 18,  2017

  

 

 

The Contractor has taken delivery of the replacement parts for the last remaining new pole to be installed. The Contractor was unable to rent the crane that is necessary to finish the last light pole this week. The proper crane is needed to safely lift the weight and height of the pole and still fit inside the park. A date of which the crane will be back has yet to be determined.

 

 

 